JBDS has recently completed the Waste Water Drainage Package on the new Tottenham Hotspur Football Stadium Development. Working on the Project with Project Manager MACE and Main Contractor Morrisroe, the works have been running for 12 weeks, with completion being scheduled for mid-November.

The works consisted of shaft excavations, Timber Headings and Open cut works to construct the drainage across all aspects of the new stadium. Part of the multi Million-pound project, JBDS were engaged throughout the design process, ensuring that the best solutions were optimised.

JBDS liaised with Internal Stakeholders, Haringey Council and Residents to ensure the works were carried out with minimal disruption and maximum efficiency.

JBDS were originally employed directly by Tottenham Hotspur Football Club to carry out Site Investigation works.  We carried out trial holes all around the existing White Hart Lane stadium prior to demolition to ascertain existing services and possible obstructions.  Once these Investigations were completed, the findings were drawn up and submitted to THFC’s design team to use in initial design of new service installations.

More News From JBDS

JBDS Wins One Nine Elms Contract

JBDS Awarded the Low Level 1 Trunk Sewer Diversion at the R&F One Nine...

JBDS Awarded Health and Safety Award

We are delighted to have received a Safety, Health and Environment award for...

JBDS Host Charity Boxing Match

JBDS hosted a charity boxing match on the 6th February in aid of our...

JBDS wins ISO 45001 Certification

We are delighted to announce that JBDS is now ISO 45001 certified for 2018...

Props Breakfast

JBDS sponsored a table in support of Variety at the Props Breakfast. Opened by...

New Year New Look

We are delighted to have received a Safety, Health and Environment award for...

Need a Solution?

We engineer bespoke solutions to meet challenging timescales and budgets.

Our preference is to consult during the early stages of a project enabling us to offer more value through our hands on experience and expertise.

White Arrow